top of page

March 1st, 2022

April 1st, 2022

We are ready to lift some containers!

January 28th, 2022

January 10th, 2022

December 1st, 2021

November 9th, 2021

Rail installation at the Mid-Willamette Valley Intermodal Center. Now laying ballast rock, under an Oregon rainbow!

November 2nd, 2021

October 10th, 2021

IMG_0328.JPEG

Crews continue to installing track between 10-ft wide concrete runners, that will serve as the travel path for Rubber Tired Gantry Crane.

October 10th, 2021

IMG_0333.JPEG

Newly poured concrete runner, with rail yard behind.

September 29th, 2021

September 15th, 2021

September 1st, 2021

August 5th, 2021

July 8th, 2021

July 26th, 2021

Retaining Wall Base 2.jpg

Grading is underway near the south end of the site.  The ground is prepared for the installation of short retaining wall that will run parallel to the south track lead into the Mid-Willamette Valley Intermodal Center.

July 14th, 2021

rebar for concrete.jpg

Rebar is staged for the construction of concrete runners.  Concrete runners will be the travel surface for large rubber tired Gantry Cranes that lift containers on and off the trains.

July 8th, 2021

June 1st, 2021

May 28th, 2021

I-5 Sign_052821.jpg

See us from I-5, project signage is installed!  We would like to thank ODOT, Connect Oregon, Key Bank and all our professional partners for helping us successfully begin the construction phase of the Mid-Willamette Intermodal Center. 

May 17th, 2021

Site Grading_051721.jpg

Site Work continues steadily.  Rotschy Construction Company is working closely with Engineering and Environmental teams to ensure the last remnants of decommissioned mill infrastructure and building foundations are removed, re-used as rubbelized fill or disposed of properly.

May 14th, 2021

Rubblization 1_051421.JPG

Final preparations are underway for bulk excavation efforts to begin next week.

May 3rd, 2021

Rubblization_050321.JPG

Demolition and rubblization of remaining site foundations are on-going.  Concrete is crushed to spec and stockpiled for use.

Mid-Willamette Valley Intermodal Center

Board of Directors

MVICBoard@mvic-intermodal.com

(c) Mid-Willamette Valley Intermodal Center (MVIC) | 2021

bottom of page