Mid-Willamette Valley
Intermodal Center
Millersburg, Oregon
March 1st, 2022
April 1st, 2022

We are ready to lift some containers!




January 28th, 2022




January 10th, 2022




December 1st, 2021




November 9th, 2021

Rail installation at the Mid-Willamette Valley Intermodal Center. Now laying ballast rock, under an Oregon rainbow!
November 2nd, 2021




October 10th, 2021

Crews continue to installing track between 10-ft wide concrete runners, that will serve as the travel path for Rubber Tired Gantry Crane.
October 10th, 2021

Newly poured concrete runner, with rail yard behind.
September 29th, 2021




September 15th, 2021




September 1st, 2021




August 5th, 2021




July 8th, 2021
July 26th, 2021

Grading is underway near the south end of the site. The ground is prepared for the installation of short retaining wall that will run parallel to the south track lead into the Mid-Willamette Valley Intermodal Center.
July 14th, 2021

Rebar is staged for the construction of concrete runners. Concrete runners will be the travel surface for large rubber tired Gantry Cranes that lift containers on and off the trains.
July 8th, 2021




June 1st, 2021




May 28th, 2021

See us from I-5, project signage is installed! We would like to thank ODOT, Connect Oregon, Key Bank and all our professional partners for helping us successfully begin the construction phase of the Mid-Willamette Intermodal Center.
May 17th, 2021

Site Work continues steadily. Rotschy Construction Company is working closely with Engineering and Environmental teams to ensure the last remnants of decommissioned mill infrastructure and building foundations are removed, re-used as rubbelized fill or disposed of properly.
May 14th, 2021

Final preparations are underway for bulk excavation efforts to begin next week.
May 3rd, 2021

Demolition and rubblization of remaining site foundations are on-going. Concrete is crushed to spec and stockpiled for use.